Following received from EA yesterday:
Work has finished at Marlow and Marsh and both locks have re-opened.
The recent floods stopped work at a number of sites resulting in some closures needing to be extended.
Iffley lock will now be closed until 8 March, and Abingdon Lock until 21 March.
Penton Hook Lock will need an additional closure from 3-31 January.
We will update the website and issue a revised Investment Programme Notice (issue 4) shortly.