Following just received:
At the RUG 7 meeting last Tuesday we were informed that Chertsey lock which was scheduled to re-open today, should re-open tomorrow.
Works on Sunbury new lock are running slightly behind schedule. The new lock was due to re-open on the Saturday 17 March 2012 however it is now due to re-open on Thursday 22 March 2012. Please note: Sunbury old lock will remain open during the new lock closure. Passage will be limited to published lock keeper hours of duty.
At the RUG 7 meeting last Tuesday we were informed that Chertsey lock which was scheduled to re-open today, should re-open tomorrow.