Listed below are the locks that will be closed during the 2017 to 2018 investment programme. The locks will be closed from the first date listed and re-open the day after the final date.
[TABLE="width: 712"]
[TR]
[TH]Location[/TH]
[TH]Date[/TH]
[TH]Work being carried out[/TH]
[TH]Canoe portage with care during closure[/TH]
[/TR]
[TR]
[TD]Shifford Lock[/TD]
[TD]30 October 2017 to 16 January 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Clifton Lock[/TD]
[TD]2 January 2018 to 23 March 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Blakes Lock[/TD]
[TD]30 October 2017 to 23 March 2018[/TD]
[TD]Repairing and re-sheeting lock gates, refurbishing lock chamber walls, replacing rubbing timbers and general repairs to the lock site area[/TD]
[TD]No[/TD]
[/TR]
[TR]
[TD]Bell Weir Lock[/TD]
[TD]30 October 2017 to 15 December 2017[/TD]
[TD]Replacing lock chamber rubbing timbers[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Molesey Lock[/TD]
[TD]30 October 2017 to 1 January 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Teddington Lock (barge)[/TD]
[TD]1 January 2018 to 23 March 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[/TABLE]
Full notice here:
https://www.gov.uk/government/publi...iver-thames-investment-programme-2017-to-2018
[TABLE="width: 712"]
[TR]
[TH]Location[/TH]
[TH]Date[/TH]
[TH]Work being carried out[/TH]
[TH]Canoe portage with care during closure[/TH]
[/TR]
[TR]
[TD]Shifford Lock[/TD]
[TD]30 October 2017 to 16 January 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Clifton Lock[/TD]
[TD]2 January 2018 to 23 March 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Blakes Lock[/TD]
[TD]30 October 2017 to 23 March 2018[/TD]
[TD]Repairing and re-sheeting lock gates, refurbishing lock chamber walls, replacing rubbing timbers and general repairs to the lock site area[/TD]
[TD]No[/TD]
[/TR]
[TR]
[TD]Bell Weir Lock[/TD]
[TD]30 October 2017 to 15 December 2017[/TD]
[TD]Replacing lock chamber rubbing timbers[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Molesey Lock[/TD]
[TD]30 October 2017 to 1 January 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[TR]
[TD]Teddington Lock (barge)[/TD]
[TD]1 January 2018 to 23 March 2018[/TD]
[TD]Re-sheeting lock gates[/TD]
[TD]Yes[/TD]
[/TR]
[/TABLE]
Full notice here:
https://www.gov.uk/government/publi...iver-thames-investment-programme-2017-to-2018