tico
Well-Known Member
Interesting... theres a Pearl 55 'Temptation' at our marina in West Wales..... His previous?
Well that answers that question in which case Pearl provided the rope with which to hang themselves. I can't imagine why a manufacturer would voluntarily put that information in a sale contract. Is it normal for buyers of new boats to demand that the laminate schedule be stated in the sale contract? Jfm, do you do this with Fairline?As to the discussion about whether or not Pearl (or those acting on their behalf) should have revealed the 20mm specification and how this was revealed, the answer is simple in that it was part of the contract which, no doubt, the claimant held already.
That's a very valid and relevant Q but no one can answer without knowing the contract between Pearl and the moulder. If the contract so provides the moulder might resist the claim on the footing that the £££ loss arose because Pearl screwed up the legal case rather than because of the moulding defect. That would make an interesting bit of litigation!I feel it's worth repeating the question - According to an earlier response from Iain, Pearl were using a Moulding Contractor to make the hull. Is it possible for Pearl to claim damages from them, as they were the ones that didn't build the hull to spec?
no it's not normal on this class of boat and I don't have it with fairline. That said, fairline know how to mould and I went to the factory often to see things. At various stages I asked them to change things and we agreed various sensible things along the way. All that is much better than a contractWell that answers that question in which case Pearl provided the rope with which to hang themselves. I can't imagine why a manufacturer would voluntarily put that information in a sale contract. Is it normal for buyers of new boats to demand that the laminate schedule be stated in the sale contract? Jfm, do you do this with Fairline?
Fully agreed, but regardless of that I can't help thinking that Pearl should have spotted the problem while building the boat anyway.no one can answer without knowing the contract between Pearl and the moulder.
Wow, changes on the moulding process? Now, that's interesting.fairline know how to mould and I went to the factory often to see things. At various stages I asked them to change things and we agreed various sensible things along the way.
its quite important that legal proceedings are fair and not conducted according to off the cuff laymanish views. It's important the claimant can make whatever sensible claim he wishes, and have his day in court. In this case the claimant CHOSE to lead on the contract argument not the fit for purpose argument. It's generally seen as a fundamental freedom that he be allowed to do that, even if you think differently.laymans law perspective.... - its the 7mm thickness that resulted in the claim ....
Arguing over crack size / waterflow -I do not think helps -or wether that he was doing 2 knots or 20 knots .....
Was it fit for purpose....
No calculation beats a picture which paints a 1000 words .
The crack was 6 inches....
i completely agree that. Any decent boat builder should have noticed that when drilling the holes for the P bracketsFully agreed, but regardless of that I can't help thinking that Pearl should have spotted the problem while building the boat anyway.
It's not like the thickness was 19.5 rather than 20, you know... :ambivalence:
Agreed. In the end a decision to buy a particular product is not about what's included or not included in the contract but about the trust that the buyer places in the seller to deliver the product to a satisfactory quality and the trust that the buyer has in the seller to put it right when it (inevitably) goes wrong. You could say that if a boat buyer has so little confidence in the manufacturer that he insists on putting the laminate schedule in the sale contract, then he's probably buying from the wrong manufacturerno it's not normal on this class of boat and I don't have it with fairline. That said, fairline know how to mould and I went to the factory often to see things. At various stages I asked them to change things and we agreed various sensible things along the way. All that is much better than a contract
Yes and it would also depend on which country's law applied to the contract. If the hull was moulded in Turkey, then the moulding company would probably have insisted on the contract being governed by Turkish law. Good luck to Pearl on that one. I would guess that if Pearl are still doing business with this company, they would horse trade a financial settlement rather than resort to lawyorsThat's a very valid and relevant Q but no one can answer without knowing the contract between Pearl and the moulder. If the contract so provides the moulder might resist the claim on the footing that the £££ loss arose because Pearl screwed up the legal case rather than because of the moulding defect. That would make an interesting bit of litigation!
Why did they reveal that the hull thickness should have been 20mm in the first place?
Well that answers that question in which case Pearl provided the rope with which to hang themselves. I can't imagine why a manufacturer would voluntarily put that information in a sale contract. Is it normal for buyers of new boats to demand that the laminate schedule be stated in the sale contract? Jfm, do you do this with Fairline?
I feel it's worth repeating the question - According to an earlier response from Iain, Pearl were using a Moulding Contractor to make the hull. Is it possible for Pearl to claim damages from them, as they were the ones that didn't build the hull to spec?
No it's Taiwan rafiki, at least for the 75. Iain smallridge himself told me that while showing me the 75 hull #1
Pearls problem is that it was not able to prove that the boat would still have suffered the same damage if it had been built to the design. Their argument rests on their belief that the forces in the grounding were far higher than the claimant claimed supported by their belief that the original crack was 30" long which would have included parts of the hull that were to specification. (It is assumed, but not stated that the crack was in the thin part of the laminate).
All agreed as a summary Tranona, except I'd say the insurers produced a pretty flaky story rather than a good one, but won the day because Pearl's lawyers/experts were so bad that they didn't spot the gaping holes in the story. (Especially the reliance upon the 40% factor in the maths which was manifestly a mistake, the fluid flow calcs generally, and the dismissal of the crack-close-up theory with no evidence as to why it ought to be dismissed)What this case seems to show from the way I see it, is that in the absence of hard facts you have to fall back on deductions made by "experts" based on what facts are known, and the winner is the one whose story is the most believable. In this case, a large sum was involved and the claimant (the insurer) was prepared to fund the preparation of a good story to persuade the court.
isn't strictly right. It was agreed that the onus of proof (that the boat wouldn't have sunk if built correctly) lay with the insurance company."Pearls problem is that it was not able to prove that the boat would still have suffered the same damage if it had been built to the design"
FE analysis is all very well, but I am mildly surprised that, in view of sums at stake, nobody seems to have done any experiments. It wouldn't have cost that much to mould the mounting recess and, say, 1m all around it in 7mm and 20mm and then hit 'em. Even doing it a few times might have been worthwhile.
Wow, changes on the moulding process? Now, that's interesting.
Can't recall to have read anything about that, care to tell us more?![]()
Yes Tranona thats stating the obvious. The only document given to the Buyer confirming RCD status would have been the CE certificate and that certainly would not contain the laminate schedule so the question remains as to how the Buyer got the laminate schedule or at least the 20mm figure. Either it was stated in the contract which seems unlikely or Pearl volunteered the information in another way which as I say, was stupid. Yes then, having made that error, Pearl's only defence was to try to prove that the damage would have happened even if the laminate was correctly constructed and in this, of course, they failed.They did not give the "rope to hang themselves". Paragraph 7 of the report explicitly states that the claim was for a breach of 1.1 of the contract, which I would imagine defines the boat that is to be supplied. Therefore it is not unreasonable to expect the boat to be built as designed because it does not exist at that time. In order to be built to conform to the RCD the design must be approved, including the lamination schedule would be a prerequisite of getting approval. If the boat is not built to the design specification it is therefore a breach of the contract. This case is about determining whether that breach led to the loss the claimant suffered.