tonybarebones
Member
After post welding inspection by the company repairing the gate, the inspector found
two further hairline cracks, despite the gate being inspected for cracks when first delivered. And none being identified.
The marina operators therefore requested the entire gate be tested with ultra-sonics. The test revealed three more cracks. All cracks have now been ground out and welded.
The anticipated date of its return to Watchet is around 28th May 2015.
The plan is to reinstall the gate in the first week of June using a mobile crane on the North East Pier once all the relevant criteria including that laid down
by the District Council are met. Structural engineers are considering the ground conditions as no records exist.
If the East Pier cannot be used the marina operators will bring a crane barge into the Outer Harbour.
Once the gate is in place it will lie flat and the marina will continue to be operated utilising stop logs until the ram and electronics are installed.
The entire hydraulic and electronic operating system is being updated and/or replaced. The whole project has been slowed down by the simple fact that
it has been found that all of the original construction drawings for the site refer to the gate in its original incarnations as a mechanical system later
topped up with a different hydraulic system. The ram has had to be redesigned from scratch as it is a custom unit.
In the meantime the marina has continued to undertake dredging in the Outer Harbour on behalf of the Landlords. This should improve access depths as well as
hopefully reduce the mud inflow into the marina itself.
Some dredging has taken place in the marina but not a full programme as there is little point until the gate is in and working. Once this is completed a
substantial dredge programme will commence.
The marina is open to visitors but advise people phone ahead first so as to advise of the access restrictions. There will be severe restrictions when the
gate is reinstalled.
James Burnell
Marina Manager
Watchet Harbour Marina
01984 631264
two further hairline cracks, despite the gate being inspected for cracks when first delivered. And none being identified.
The marina operators therefore requested the entire gate be tested with ultra-sonics. The test revealed three more cracks. All cracks have now been ground out and welded.
The anticipated date of its return to Watchet is around 28th May 2015.
The plan is to reinstall the gate in the first week of June using a mobile crane on the North East Pier once all the relevant criteria including that laid down
by the District Council are met. Structural engineers are considering the ground conditions as no records exist.
If the East Pier cannot be used the marina operators will bring a crane barge into the Outer Harbour.
Once the gate is in place it will lie flat and the marina will continue to be operated utilising stop logs until the ram and electronics are installed.
The entire hydraulic and electronic operating system is being updated and/or replaced. The whole project has been slowed down by the simple fact that
it has been found that all of the original construction drawings for the site refer to the gate in its original incarnations as a mechanical system later
topped up with a different hydraulic system. The ram has had to be redesigned from scratch as it is a custom unit.
In the meantime the marina has continued to undertake dredging in the Outer Harbour on behalf of the Landlords. This should improve access depths as well as
hopefully reduce the mud inflow into the marina itself.
Some dredging has taken place in the marina but not a full programme as there is little point until the gate is in and working. Once this is completed a
substantial dredge programme will commence.
The marina is open to visitors but advise people phone ahead first so as to advise of the access restrictions. There will be severe restrictions when the
gate is reinstalled.
James Burnell
Marina Manager
Watchet Harbour Marina
01984 631264