for those who use the essex section's of the M25 , had this update from the highways agency .
The next section of work will be between junction 28 (A12) and junction 29 (A127) and starts next month.
This initial work is planned to run from July to November this year and they will be widening the anti-clockwise section of carriageway.
Further dates for this section of the M25 will be approximately:
November to March 2011 - widening the clockwise carriageway (junction 28 to 29)
March to May 2011 - working in the centre reserve (junction 28 to 29)
Following this work, they will be widening the last section from junction 29 (A127) to junction 30 (A13). These works are planned to start July/August time in 2011.
maybe of some use to some of the essex people ,
Nige.
The next section of work will be between junction 28 (A12) and junction 29 (A127) and starts next month.
This initial work is planned to run from July to November this year and they will be widening the anti-clockwise section of carriageway.
Further dates for this section of the M25 will be approximately:
November to March 2011 - widening the clockwise carriageway (junction 28 to 29)
March to May 2011 - working in the centre reserve (junction 28 to 29)
Following this work, they will be widening the last section from junction 29 (A127) to junction 30 (A13). These works are planned to start July/August time in 2011.
maybe of some use to some of the essex people ,
Nige.